S/N | JOB DESCRIPTION | CLIENT COMPANY | LOCATION | CLIENT CONTACT(S) | DURATION | REMARKS |
---|---|---|---|---|---|---|
1 | GRIT BLASTING AND PAINTING WORKS - TANK REPLACEMENT AND UPGRADE (TRU) PROJECT (TANK 9) | BAYWOOD DEXTRON VENTURES (BDV) &
CHEVRON NIGERIA LIMITED (CNL) |
CHEVRON ESCRAVOS TERMINAL TANK FARM | BDV – Engr. Chris Ugwu (Project Director) – 08052446275
CNL – Engr. Chijioke Omeile (CNL TRU Rep) – 08025887845 |
December 2015 | COMPLETED |
2 | GRIT BLASTING AND PAINTING OF THE PPMC MANIFOLD | CHEVRON NIGERIA LIMITED | CHEVRON ESCRAVOS TERMINAL | ENGR. MIKE UGWU/
ENGR. OSAZEE ONAGHINOR (CNL TRU REP) 08055889093 |
2014 | COMPLETED |
3 | MAINTENANCE PAINTING WORKS ON BLACK JACK LIFT BOAT; BLASTING AND PAINTING OF DECK, HULL, BOTTOM AND RUDDER TANKS | HERCULES OFFSHORE NIGERIA LIMITED (HONL) | HERCULES OFFSHORE YARD | Alvin Pierce (Shipyard Manager) – 08058062822
Jeff Urhie (Assistant Shipyard Manager) – 08055306400 |
2012 TO 2013 | COMPLETED |
4 | MAINTENANCE PAINTING WORKS ON DURWOOD SPEED LIFT BOAT; BLASTING AND PAINTING OF HULL AND BOTTOM | 2012 to 2012 | COMPLETED | |||
5 | GRIT BLASTING AND PAINTING WORKS – TANK REPLACEMENT AND UPGRADE (TRU) PROJECT (TANK 3) | BAYWOOD DEXTRON VENTURES (BDV) & | CHEVRON NIGERIA LIMITED (CNL) | BDV – Engineer Chris Ugwu (Project Director) – 08052446275 | 2012 to 2012 | COMPLETED |
6 | GRIT BLASTING AND PAINTING WORKS – TANK REPLACEMENT AND UPGRADE (TRU) PROJECT (TANK 5) | CHEVRON NIGERIA LIMITED (CNL) | CHEVRON NIGERIA LIMITED (CNL) | CNL – Engr. Chijioke Omeile (CNL TRU Representative) – 08025887845 | 2007 to 2010 | COMPLETED |
7 | MAINTENANCE PAINTING WORKS ON BLUE SHARK LIFT BOAT; BLASTING AND PAINTING OF BALLAST, VOID AND WATER TANKS, DECK, HULL AND BOTTOM | HERCULES OFFSHORE NIGERIA LIMITED (HONL) HERCULES |
HERCULES OFFSHORE NIGERIA LIMITED (HONL) HERCULES |
George Smesko (Operations Manager) – 08033528983
Alvin Pierce (Shipyard Manager) – 08058062822 |
2009 to 2010 | COMPLETED |
8 | MAINTENANCE PAINTING WORKS ON PILOT FISH LIFT BOAT; BLASTING AND PAINTING OF BALLAST TANKS,RUDDER ROOM, HULL AND BOTTOM SIDE | COMPLETED | ||||
9 | GRIT BLASTING AND PAINTING OF GRAND STAFF JACK-UP BARGE; 4 VOID TANKS AND TOP DECK | HALLIBURTON ENERGY SERVICES LIMITED | HALLIBURTON ENERGY SERVICES LIMITED | George Smesko – 08033528983 | 2005 to 2009 | COMPLETED |
10 | BONGA MODULE FABRICATION LOAD OUT; A SEA FASTENING PROJECT FOR SNEPCO–GRIT BLASTING & PAINTING (LAY DOWN MODULE, SALES GAS MODULE & GAS FLARE BOOM) | DAEWOO NIGERIA LIMITED | DAEWOO NIGERIA LIMITED | Y.W. Lee (Deputy Construction Manager) – 053-254354 | 2002 to 2003 | COMPLETED |